What Happens Behind the Interconnection Black Box, From Application to Approval
For many developers, the period between submitting an interconnection request and receiving approval can feel like a black box. Years may pass before reaching an executable agreement, with little visibility into what's being studied, how costs are developing, or when key decisions need to be made.
This session pulls back the curtain on the cluster study process established under FERC Order No. 2023. It covers how projects are evaluated, how network upgrades are identified, how costs are allocated, and how interactions among projects in a cluster can shift outcomes.
Developers are often required to make significant commercial decisions on short timelines, sometimes with only a few weeks to determine whether additional capital should remain at risk. Successful developers prepare for these moments in advance by understanding the range of possible outcomes, evaluating upgrade exposure early, and setting clear investment criteria before results arrive.
Attendees will leave with a clearer understanding of the timeline, the milestones that matter most, and how to manage interconnection risk proactively rather than reactively.
Key takeaways
- A clear map of the cluster study lifecycle and the major decision points along the way, including when developers may need to commit additional capital, provide financial security, or determine whether a project remains commercially viable.
- A practical explanation of how network upgrades and associated costs are identified and allocated, and why outcomes can change as other projects enter, withdraw from, or move through the cluster.
- Strategies for becoming a proactive participant in the interconnection process, including how to prepare for study results, evaluate upgrade exposure, and make informed decisions when critical milestones are reached.
Presenter:
John Bernecker
John is the Interconnection Technical Director at E Source, where he helps generation and large-load developers navigate the interconnection process from site selection through commissioning. His expertise spans transmission planning, power system analysis, electric system reliability, regulatory strategy, and ISO/RTO interconnection processes. Previously, John founded NYSERDA’s Transmission Center of Excellence and held leadership roles in transmission planning and resource integration at ERCOT. He holds degrees from Penn State, Columbia University, and the George Washington University, and is a licensed Professional Engineer.
TRANSCRIPT
Hello, everyone, and welcome. My name is Matt Besh. I'm the grid marketing lead at E Source.
I'm really happy you're here for today's session, what happens behind the interconnection black box from application to approval. Before I, like, get rolling on this, some housekeeping. We're gonna be together for about the next thirty minutes or so.
Everyone that registered, we're gonna give you a recording afterwards.
And along the way, if you do have questions, go down to the bottom of your screen, click the chat button and drop them in the chat. We're gonna try to leave about five minutes towards the end for our panel or our presenter, John, to answer your questions.
Now as for the topic, if you've ever submitted an Interconnection request, you know how the process feels.
Years can pass between application and an agreement, often with limited visibility in what's being studied, what costs, how costs are being developed, and really what, when you'll need to decide whether more capital goes into project. These are decision points. Today is all about pulling back the curtain on that process, so you know what's happening at each stage and where the key decisions get made.
Now, back to the housekeeping, a little bit about eSource.
This is kind of the drill. For about forty years or so, we've helped energy stakeholders solve really complex problems.
ESource brings deep, great engineering expertise to the energy industry, and we've really worked across the spectrum with ISOs, utilities, developers, IPPs, you name it. Our interconnection team supports developers from site selection through commissioning, and really has the benefit of having seen this process from every every side.
This kind of brings me to the panel, to the presenter today, John Boernicker. He's, I'm really excited about this. He's eSource's interconnection technical director, brings a wealth of experience to this conversation.
Before joining us, he managed the transmission planning at ERCOT, and during his time there, he coordinated the generation interconnection process from feasibility studies all the way through commissioning. He then founded NYSERDA's Transmission Center of Excellence.
It is a wealth of knowledge, and I think we're all going to learn something today from John. John, the floor is yours. Take it away.
Thanks, Matt, and welcome, everyone. Thank you for joining us. Today, we're going to look at what happens in cluster studies between the filing of an interconnection application and the execution of an interconnection agreement. For many developers, that process can feel a bit like a black box.
A project enters the process with a defined capacity, configuration, point of interconnection, and target commercial operation date. Months or years later, it may emerge with significant network upgrades, a different schedule, new security requirements, or an entirely different investment outlook.
Our goal today is to make that process more transparent. We'll explain what the utilities and ISOs are studying, how projects within a cluster affect one another, where cost and schedule surprises originate, and how developers can prepare for the key decisions that follow.
To understand that process, we should first understand what ISOs and utilities are solving for. Cluster studies comprise a set of technical evaluations of the steady state, short circuit, and stability impacts of projects in the cluster, and identification of network upgrades required to interconnect those projects. In conducting those evaluations, ISOs and utilities are trying to address four interrelated questions.
First, can the system accommodate the project's injection or withdrawal without overloading transmission facilities or producing unacceptable voltage performance?
Second, do fault duties remain within equipment capabilities and protection settings when a new resource or facility is added?
Third, does the system remain stable following model disturbances, and do generators, inverter based resources, and their controls interact acceptably with the grid?
And fourth, if the study identifies violations of performance criteria, which reinforcements resolve those, and which projects drive or benefit from those reinforcements.
It's important to understand that the process is evaluating how the entire cluster impacts the system, not simply whether an individual project can connect.
Three characteristics make this process feel opaque from the developer's perspective.
The first is the timeline. The period from application to interconnection agreement can extend over several years. Individual study phases may take many months, and the project may receive limited insight into the ultimate cost and schedule outcomes until formal results are issued.
The second is interactions with other projects. A cluster study does not simply look at whether one project can interconnect on its own. It evaluates the combined effect of all projects represented in the study case. That means the outcome depends not only on a given project's design, but also on the size, location, technology, operating assumptions, and eventual decisions of other projects. Developers have limited foresight into how their project may interact with others within the cluster.
And the third issue is the speed with which developers must make major investment decisions when results become available. After waiting months for results, a developer may only have a few weeks to decide whether to put more capital at risk or accept withdrawal penalties, and those financial commitments and potential withdrawal consequences only increase as cluster studies progress.
In short, the black box experience is the result of a long period of uncertainty, followed by a short period in which multimillion dollar decisions must be made.
While the specific labels and sequencing can vary by region, cluster study processes can be thought of as consisting of four broad stages.
The first is application and readiness, which establishes whether the project is sufficiently complete to enter the cluster study. At this point, the utility or ISO validates the project's technical information, models, site control documentation, and applicable deposits.
The second stage is system impacted deliverability analysis. Study cases are finalized, then steady state short circuit instability analyses are performed. Projects may also be screened to determine whether more detailed electromagnetic transient analysis is needed.
At the end of this phase, preliminary network upgrades and initial cost allocation are identified.
The third stage is restudy and final cost allocation. If projects withdraw or material assumptions change, study cases may need to be updated, analyses rerun, upgrades reevaluated, and cost allocations revised.
The final stage is execution of the interconnection agreement, where cost obligations, financial security requirements, and milestones leading to commercial operation are memorialized.
We see six common pitfalls that can put projects at risk when navigating the interconnection process.
The first of those is incomplete models where failed validation can delay the study start or even prevent the project from entering cluster. And that can result in a delay of years if they have to wait for the next cluster in order to take the project through the interconnection process.
The second is late design changes. Material equipment or configuration changes may require additional analysis or restudy.
The third is an optimistic schedule that does not account for the full study duration, including potential restudies or network upgrade dependencies.
The fourth is unexpected upgrade exposure. If the project economics cannot support a reasonable range of shared upgrade costs, the project may not be resilient enough to reach commercial operation.
The fifth is a restudy blind spot where the team evaluates initial study results but does not test how withdrawals and the resulting revised cost allocations could affect the project.
And the sixth is slow decision making, where internal approvals, financing reviews, or investment committee processes do not move quickly enough to meet formal decision deadlines.
Network upgrade exposure is one major factor affecting project economics as they go through these processes.
The upgrade set is influenced by the base case topology and dispatch, the project size and location, its operating assumptions, other projects in the cluster, and the applicable contingencies and performance criteria used for the study.
These inputs determine which issues are identified and which upgrades are selected to resolve them.
But identifying an upgrade is only part of the picture.The next question is how responsibility for that upgrade is allocated. Cost allocation can move because several projects may use the same facility or drive the same network upgrade. Projects may withdraw, altering the underlying needs for network upgrades. The scope of those upgrades may be revised, and the underlying cost estimate may change as engineering progresses.
Those realities highlight a key point.
A project may change, may not change, yet its assigned costs can, which is why network upgrade exposure should be treated as a range of potential outcomes rather than a single number.
This example illustrates how withdrawals from a cluster can can impact cost allocation for the remaining projects in that cluster.
Suppose the initial study assigns a project $45,000,000 in network upgrades.
The target commercial operation date remains supportable, and the relevant shared upgrades are funded across three projects.
Then a nearby project withdraws, and the shared upgrade responsibility must be reconsidered. The utility or ISO determines whether the original upgrade remains appropriate, whether the cost allocation changes, and whether the revised scope affects the schedule.
Following restudy in example, the project is now assigned $70,000,000 in network upgrades, and the commercial operation date is delayed. Management must now make a new decision about whether to proceed. Nothing about the project necessarily changed, but the cluster around it did. These values are illustrative, but the decisions are real.
The developer must now determine whether the project can absorb $25,000,000 in additional costs and a delay in schedule, or whether withdraw is the better decision.
That example from the last slide highlights one of four points in the process where technical results become executive decisions. Looking at those decision points in order, we start with entry, where the fundamental question is whether the project is mature enough to post the required deposits and accept the exposure to financial risk associated with entering the study.
The second is the initial study result. Do the assigned upgrade costs, schedule, and remaining uncertainty still fit the project's investment thesis.
The third restudy was highlighted in our example. Can the project absorb a change in cost allocation or schedule after the cluster changes?
And the fourth is the interconnection agreement. Are the financial security procurement requirements, milestones, cost obligations, and withdrawal provisions financeable and executable?
These decisions should not be treated as routine administrative approvals.
Each one is an opportunity to revisit the development thesis using the best available technical and commercial information.
Ensuring project readiness before entering the cluster itself is a key opportunity for developers to manage risk prior to the formal study beginning. Technical packages must be complete with consistent project models, equipment specifications, control assumptions, and point of interconnection definition.
Commercial assumptions should be realistic. The requested capacity, technology, target commercial operation date, and site strategy should reflect the project that the developer actually intends and is able to build.
And related to that last point is change discipline. Changes in major equipment such as inverters, plant configuration, output capability, or other material equipment assumptions may require additional review, lead to delay, or result in change study outcomes.
While some changes may be unavoidable, submitting projects for which changes are expected comes without a risk.
So now let's focus on how developers can prepare for key decision points. Before filing an application, screen interconnection risk and potential upgrade exposure early. Set the framework for evaluating network upgrade exposure and restudy scenarios, and validate models before submission.
While studies are underway, monitor cluster developments and track assumptions that may affect the project, update evaluations of interconnection risk and network upgrade exposure, and conduct sensitivity analysis around potential project withdrawals.
And before a formal decision deadline, establish cost, schedule, and risk thresholds, and identify related go, no go scenarios for the project.
While developers cannot control system conditions or the decisions of neighboring projects in the cluster, they can control the quality and technical readiness of their submitted project, the amount of early risk screening that they perform, the clarity of the decision criteria that they establish, and the speed of their internal reviews.
That makes the difference between preparing for a range of results versus reacting to a result after the available options have narrowed.
Starting to tie things together, I'd like to leave you with three takeaways.
First, cluster studies are not only technical analyses, but a series of business decisions informed by technical results.
Second, the most important decisions often occur under tight deadlines immediately after results are issued.
Third, projects that define costs, schedule, and risk thresholds early can evaluate results and act more quickly when the decision window opens.
You may not be able to predict the exact set of network upgrades or restudy outcomes, but you can identify the range of credible outcomes, understand which assumptions drive them, and decide how to respond in advance.
So thank you for joining us.
Please feel free to reach out if you would like to discuss a specific project, study result, upcoming decision point. And if you're attending RE plus please stop by and say hi. We'd love to chat with you.